| Dallam-Sherman |
TX |
115 kV |
$14.5 million |
In-service |
| Hitchland-Moore |
TX |
230 kV |
$37 million |
In-service |
| Hitchland-Ochiltree |
TX |
230 kV |
$28 million |
In-service |
| Amarillo South-Randall County |
TX |
230 kV |
$21 million |
In-service |
| Newhart-Kress |
TX |
115 kV |
$15 million |
March 21, 2014 |
| Kiser-Cox |
TX |
115 kV |
$6.4 million |
March 7, 2014 |
| Newhart-Castro |
TX |
115 kV |
$15.6 million |
January 10, 2014 |
| Hitchland-Woodward |
TX |
345 kV |
$60 million |
May 1, 2014 |
| TUCO-Woodward |
TX |
345 kV |
$205 million |
September 26, 2014 |
| Newhart-Lamton |
TX |
115 kV |
$18.7 million |
November 11, 2014 |
| Kiser-Kress |
TX |
115 kV |
$15.1 million |
November 21, 2014 |
| Newhart-Swisher |
TX |
230 kV |
$19.5 million |
December 15, 2014 |
| Pleasant Hill-Oasis-Roosevelt |
NM |
230 kV |
$45 million |
January 27, 2015 |
| Rolling Hills-Hastings |
TX |
115 kV |
$26 million |
March 13, 2015 |
| Hopi-North Loving-China Draw |
NM |
115 kV |
$48 million |
May 25, 2015 |
| Quahada Switching Station |
NM |
n/a |
$8 million |
July 9, 2015 |
| Diamondback-Sulphur Springs |
TX |
115 kV |
$13 million |
August 14, 2015 |
| Potash Junction-Roadrunner |
NM |
230 kV |
$88 million |
October 27, 2015 |
| Kilgore-Portales |
NM |
115 kV |
$8 million |
October 27, 2015 |
| Battle Axe-Roadrunner |
NM |
115 kV |
$14 million |
November 12, 2015 |
| Ochiltree-Cole |
TX |
115 kV |
$12 million |
November 19, 2015 |
| Artesia Town-Artesia South |
NM |
69/115 kV |
$3.3 million |
November 19, 2015 |
| Dallam-Channing-Potter County |
TX |
230 kV |
$22 million |
December 15, 2015 |
| Bowers-Howard |
TX |
115 kV |
$39 million |
March 2, 2016 |
| Andrews-NEF |
NM |
115 kV |
$14 million |
April 22, 2016 |
| Ochiltree-Lipscomb |
TX |
115 kV |
$14 million |
June 22, 2016 |
| Curry-Bailey |
TX |
115 kV |
$38 million |
September 29, 2016 |
| PCA Interchange-Quahada Interchange |
NM |
115 kV |
$10 million |
February 25, 2017 |
| Wheeler-Coburn Creek |
TX |
115 kV |
$12 million |
March 15, 2017 |
| Roadrunner-Agave-Ochoa |
NM |
115 kV |
$6 million |
April 28, 2017 |
| Custer Mountain-Ponderosa |
NM |
115 kV |
$14 million |
June 1, 2017 |
| China Draw-Wood Draw |
NM |
115 kV |
$16 million |
June 15, 2017 |
| Livingston Ridge-Sage Brush-Cardinal |
NM |
115 kV |
$40 million |
November 14, 2017 |
| Custer Mountain-Whitten |
NM |
115 kV |
$4 million |
January 24, 2018 |
| Roswell Loop |
NM |
115 kV |
$24 million |
January 31, 2018 |
| Wolfforth-Carlisle |
TX |
230 kV |
$32 million |
March 27, 2018 |
| NE Hereford-La Plata |
TX |
115 kV |
$14 million |
March 30, 2018 |
| Kiowa-Roadrunner |
NM |
345 kV |
$23 million |
April 27, 2018 |
| Roadrunner-Custer Mountain |
NM |
115 kV |
$5 million |
May 11, 2018 |
| Hobbs-China Draw |
NM |
345 kV |
$140 million |
May 30, 2018 |
| Portales Loop |
NM |
115 kV |
$29 million |
July, 2018 |
| Canyon West-Dawn-Panda-Deaf Smith |
TX |
115 kV |
$13 million |
November 1, 2018 |
| Monument Tap-Byrd Tap |
NM |
115 kV |
$4 million |
November 20, 2018 |
| Atoka-Eagle Creek |
NM |
115 kV |
$21 million |
December 18, 2018 |
| NEF-Cardinal |
NM |
115 kV |
$7 million |
March 20, 2019 |
| Potash Junction-Livingston Ridge |
NM |
115 kV |
$10 million |
April 13, 2019 |